Hawthorne, CA
Home MenuDepartments » Public Works » Engineering
Capital Improvement Projects
The Project aims to minimize conflicts of turning traffic with the through traffic on El Segundo Blvd., between the 405 freeway ramps, by modifying and upgrading the intersection layout and related systems. The project will upgrade the traffic signal system on El Segundo Blvd. at the 405 freeway ramps, enhancing traffic circulation and access to the I-405. The current signal systems were installed over 2 decades ago, and have proven problematic for coordination to the adjacent traffic signal systems due to equipment break down and inaccurate time keeping in the old controllers. This project will provide new traffic signal timings to each intersection, reflecting the current traffic demand and thereby enhancing the traffic coordination and minimizing travel delays.
Project Funding: $600,000.00
- Measure R
- Public Works Street funds
Project Engineer: Dweejal (DJ) Torado
Project Status: Planning/Study Phase
Estimated Completion Date: December 2025
The project will environmentally clear, modify, and replace traffic signal system, traffic striping, adjustment of utilities, excavation and removal of existing pavement, construction of curb, gutter, sidewalks and driveways. In addition, intersection widening on Imperial Hwy. at Hawthorne Blvd. to widen Hawthorne Blvd. and to modify the existing median to construct a southbound right-turn lane on Hawthorne Blvd and add a de facto westbound right-turn lane on Imperial Hwy. The next street widening location is at Imperial Hwy and Freeman Ave which will modify median to add a second eastbound left turn lane on Imperial Hwy towards the 105 on ramp. This project will enhance pedestrian safety by upgrading the pedestrian signals with count down feature, installing safety lights at inter sections to enhance visibility of pedestrians and upgrade all ADA access ramps.
Project Funding: $3.8M
- Measure M
- Measure R
- Public Works Street funds
Project Engineer: Dweejal (DJ) Torado
Construction Inspector: Don Krause
Contractor: TBD
Project Status: Preliminary Design Underway
Estimated Completion Date: December 2025
The project proposes to widen two intersections, signal modifications, traffic coordination and timing upgrades, re-striping, utility work, reconstruction of adjacent concrete sidewalks, driveways, curbs and gutters required for the new signal poles. Currently the existing traffic signal systems were installed over 2 decades ago and have proven problematic for coordination due to equipment break down and inaccurate time keeping in the old controllers at the following locations:
- El Segundo Blvd. at Van Ness Ave.
- El Segundo Blvd. at Isis Ave
- El Segundo Blvd. at Ramona Ave.
Project Funding: $2M
- Measure R
- Public Works Street funds
Project Engineer: Dweejal (DJ) Torado
Project Status: Design Phase
Estimated Completion Date: December 2025
The project will widen intersections, add vehicular lanes, modify and upgrade traffic signal system (including ADA ramps where signal upgrade impacts the adjacent ramp) , traffic striping, adjustment of utilities, excavation and removal of existing pavement, concrete, asphalt and construction of curb, gutter, sidewalks, driveways, retaining walls, and raised medians. The intersection widening locations are at Rosecrans Ave and Inglewood, which will add a 2nd left-turn lane for both eastbound and westbound directions, and at Rosecrans Ave at Isis Ave which will add a de facto eastbound right-turn lane on Rosecrans Ave. Traffic signal system will be upgraded at each signalized intersection along Rosecrans Avenue enhancing the traffic circulation and access to I-405. The current signal systems are installed over 3 decades ago, and have proven problematic for coordination due to equipment break down and inaccurate time keeping in the old controllers. This project will also provide new traffic signal timings to each intersection reflecting the current traffic demand thereby enhancing the traffic coordination and minimizing travel delays. The project includes the intersections of Rosecrans Ave at Hawthorne Blvd, Inglewood Ave, Ocean Gate Ave, Hindry Ave, Isis Ave, and Aviation Blvd.
Project Funding: $4M
- Measure M
- Measure R
- Public Works Street funds
Project Engineer: Heecheol Kwon, Jesus Velazquez, Dweejal (DJ) Torado
Construction Inspector: Don Krause
Contractor: TBD
Project Status: Planning/ Preliminary Design cost estimate
Estimated Completion Date: December 2026
The project will widen intersections, add vehicular lanes, modify and upgrade traffic signal system (including ADA ramps where signal upgrade impacts the adjacent ramp), traffic striping, adjustment of utilities, excavation and removal of existing pavement, concrete, asphalt and construction of curb, gutter, sidewalks, driveways, and BMP devices. The intersection widening locations are at Rosecrans Ave and Prairie Ave, which will add a right-turn lane. Traffic signal systems will be upgraded at each signalized intersection along Rosecrans Avenue enhancing the traffic circulation. The current signal systems are installed over 3 decades ago, and have proven problematic for coordination due to equipment break down and inaccurate time keeping in the old controllers. This project will also provide new traffic signal timings to each intersection reflecting the current traffic demand thereby enhancing the traffic coordination and minimizing travel delays. The project includes the intersections at the following locations:
- Rosecrans Ave. at Prairie Ave.
- Rosecrans Ave. at Doty Ave.
- Rosecrans Ave. at Yukon Ave.
- Rosecrans Ave. at Cerise Ave
- Rosecrans Ave. at Lemoli Ave.
- Rosecrans Ave. at Crenshaw Blvd.
Project Funding: $2M
- Measure M
Project Engineer: Heecheol Kwon, Jesus Velazquez, Dweejal (DJ) Torado
Construction Inspector: Don Krause
Contractor: TBD
Project Status: Planning/ Preliminary Design cost estimate
Estimated Completion Date: December 2026
The project consists of excavation and removal of existing pavement, concrete and asphalt paving, construction of curb and gutter, sidewalks, driveways, storm drain, potholing and ADA ramps. In addition, work will include traffic striping, adjustment of utilities and all other work necessary to complete the improvements in accordance with the Plans and Specifications.
Approximately 11,002 Passenger Tire Equivalents (PTEs) were diverted from the waste stream by this project.
Project Funding: $3.2M
- Local Funds
- MTA Measure R
- Proposition C
- CalRecycle
Project Engineer: Jesus Velazquez
Construction Inspector: Don Krause
Contractor: Sequel Contractors, Inc.
Project Status: Under Construction
Estimated Completion Date: March 2025
Traffic signal systems will be upgraded at each signalized intersection along Crenshaw Blvd (between 120th St and Rosecrans Ave) enhancing the traffic circulation throughout this avenue. The current signal systems have been installed over 3 decades ago and have proven problematic for coordination due to equipment break down and inaccurate time keeping in the old controllers. This project will also provide new traffic signal timings to each intersection reflecting the current traffic demand, thereby enhancing the traffic coordination and minimizing travel delays. The project's goal is to enhance traffic flow towards the I-105 freeways, reduce congestion, increase pedestrian safety, and improve the efficiency of public transit use. This design will widen intersections at Crenshaw Blvd and Rosecrans Ave, add vehicular lanes, traffic striping, adjustment of utilities, excavation and removal of existing pavement, concrete, asphalt and construction of curb, gutter, sidewalks, driveways, and BMP devices. The project includes the intersections at the following locations:
- Crenshaw Blvd. at 120th St.
- Crenshaw Blvd. at Rocket Road
- Crenshaw Blvd. at Jack Northrop Ave.
- Crenshaw Blvd. at Innovative Way
- Crenshaw Blvd. at El Segundo Blvd.
- Crenshaw Blvd. at 135th St.
- Crenshaw Blvd. at Rosecrans Ave.
Project Funding: $4M
- Measure M
Project Engineer: Heecheol Kwon, Jesus Velazquez, Dweejal (DJ) Torado
Construction Inspector: Don Krause
Contractor: TBD
Project Status: Planning/ Preliminary Design cost estimate
Estimated Completion Date: December 2026
The project consists of regrading street runoff conveying systems such as street surface slope, curb and gutter and cross gutter, modifying and upgrading traffic signal systems, traffic striping and signage, pothole repair, AC resurfacing, upgrading ADA ramps, constructing sidewalks and driveways, installing storm drain inlets, pipes and BMPs devices to the following streets:
- Cedar Ave. from El Segundo Blvd. to 118th St.
- Freeman Ave. from Imperial Hwy. to El Segundo Blvd.
- Menlo Ave. from Imperial Hwy. to El Segundo Blvd.
- Oxford Ave. from Imperial Hwy. to El Segundo Blvd.
- 126th St. from Birch Ave. to Prairie Ave.
Approximately 26,473 Passenger Tire Equivalents (PTEs) were diverted from the waste stream by this project.
Project Funding: $4.3M
- Measure M Grant
- CalRecycle
Project Engineer: Heecheol Kwon, Dweejal (DJ) Torado
Construction Inspector: Don Krause
Contractor: Sequel Contractors, Inc.
Project Status: Completed
This project consists of traffic signal upgrade, trenching and installing conduits, construction of curb and gutter, sidewalks, ADA ramps, striping and adjustment of utilities. The traffic signal systems that will be replaced along 120th St. are at Prairie Avenue, York Avenue, Freeman Avenue, Birch Avenue, Grevillea Avenue, Ramona Avenue, Eucalyptus Avenue, and Felton Avenue.
Project Funding: $3.2M
- HSIP
- Measure M
- Public Works Street funds
Project Engineer: Jesus Velazquez
Construction Inspector: Don Krause
Contractor: Elecnor Belco Electric, Inc.
Project Status: Completed
The project will regrade street runoff conveying systems such as street surface slope, curb and gutter and cross gutter, modify and upgrade traffic signal systems, install flashing beacon, traffic striping and signage, pothole repair, AC resurfacing , upgrade ADA ramps, construct sidewalks and driveways, install storm drain inlets, pipes and BMPs devices to the streets below:
- 132nd St. from Prairie Ave. to Yukon Ave.
- 135th St. from Prairie Ave. to Crenshaw Blvd.
- 139th St. from Prairie Ave. to Crenshaw Blvd.
- Kornblum Ave. from 135th St. to Rosecrans Ave.
- Yukon Ave. from 134th St. to El Segundo Blvd.
- Cerise Ave. from 135th St. to Rosecrans Ave.
Project Funding: $4.6M
- Measure M Grant
Project Engineer: Heecheol Kwon, Dweejal (DJ) Torado
Construction Inspector: Don Krause
Contractor: TBD
Project Status: Design Phase
Estimated Completion Date: Spring 2026
The project will upgrade and install new traffic signals, trench and install conduits, construct curb and gutter, sidewalks, and ADA ramps, and stripe and adjust utilities at the following locations:
- Hawthorne Blvd. @ Imperial Hwy
- Hawthorne Blvd. @ 116th St.
- Hawthorne Blvd. @ 118th St.
- Hawthorne Blvd. @ 119th St.
Project Funding: $2.35M
- Measure M Grant
Project Engineer: Dweejal (DJ) Torado
Construction Inspector: Don Krause
Contractor: Elecnor Belco Electric, Inc.
Project Status: Completed
The project will remove and replace the roof system and repair any related damages to the Betty Ainsworth Gymnasium roof.
Project Funding: $787,000
- Budget Act of 2022 from the State of California
Project Engineer: German Franco
Contractor: Best Contractors Services, Inc.
Project Status: Completed
The project will repair and restore sewer pipe lines throughout the City, install new storm drain pipes, remove and restore existing surface, trench excavation, shoring and backfill, remove and replace existing sewer facilities including, but not limited to sewer mains, service connections and other appurtenances. It also includes reconstruction of existing manholes and traffic striping.
Project Funding: $2.2M
- American Rescue Plan Act (ARPA)
Project Engineer: Heecheol Kwon
Construction Inspector: Don Krause
Contractor: GRBCON, Inc.
Project Status: Completed
The project will structurally analyze the City Hall, Memorial Center and Water Tower to create plans and ensure each structure is more structurally safe and resistant to seismic activity, ground motion, or soil failure due to earthquakes. The plans will then be used for the construction phase.
Project Funding
- FEMA Grant: Bric Grant
Project Engineer: German Franco, Selena Acuna
Contractor: Labib Funk & Associates
Project Status: Completed
The project will create a new roof system, rain gutters, new fascia, and exterior surfaces patched and prepped for a new coat of paint to six (6) City-owned residential buildings.
Project Funding: $1.5M
- Home Funds
- PLHA Grant
- Maxine Waters Grant
Project Engineer: German Franco
Contractor: Best Contractors Services, Inc.
Project Status: Completed
The project will install new lights at Jim Thorpe Park baseball fields and futsal courts as well as a new electrical panel. New lights, carpet, seats/chains and a new display equipment will be installed inside the City Council Chambers.
Project Funding: $444,000
- Energy Efficiency & Conservation Block Grant (EECBG) Program
Project Engineer: German Franco
Contractor: Huntington Beach Electric, Inc.
Project Status: Under construction
Estimated Completion Date: Summer 2025
The project will upgrade the Memorial Center HVAC System from a three (3) unit system to a centralized system and a new emergency generator will be installed and integrated into the existing electrical power system.
Project Funding: $2.426M
- Budget Act of 2022 from the State of California Department of Parks and Recreation
- American Rescue Plan Act (ARPA) Fund
Project Engineer: German Franco
Contractor: Pardess Air, Inc.
Project Status: Under construction
Estimated Completion Date: Summer 2025
The project will retrofit all units in six (6) residential buildings owned by the City of Hawthorne.
Project Funding: $4.147M
- Home Funds
- PLHA Grant
- Maxine Waters Grant
Project Engineer: German Franco
Contractor: Klassic Engineering & Construction, Inc.
Project Status: Under construction
Estimated Completion Date: January 2026
The project will renovate the existing, under-utilized 0.5-acre park in the City of Hawthorne into a multi-benefit, climate resilient community space through the construction of a new playground, picnic area with shade structures, exercise equipment, half court, walking paths with mosaic art elements, perimeter fencing, restroom building, California native plants, bioswale, and other sustainable elements.
Project Funding: $3M
- State of California Department of Transportation
- Clean California Local Grant Program
- County of Los Angeles Measure A
- Baldwin Hills Urban Watersheds Conservancy (Prop 40)
Project Engineer: Selena Acuna
Construction Inspector: Don Krause
Contractor: DOJA, Inc.
Project Status: Under construction
Estimated Completion Date: Spring 2025
The project will restore various alleys throughout the City and consists of grinding, excavation and removal of existing pavement and construction of PCC pavement, curb and gutter, sidewalks, alleys, driveways and ADA ramps and adjustment of utilities.
Project Funding: $450,000
- CDBG Funds
Project Engineer: Marcial Ramos
Construction Inspector: Don Krause
Contractor: Martinez Landscape, Inc.
Project Status: Completed
The work consists of the improvement at Eucalyptus Park and Ramona Park, including Americans with Disabilities Act (ADA) accessibility. At Eucalyptus Park, this project will remove and replace the existing play equipment and install a new mini soccer field. At Ramona Park, this project will remove and replace the existing play equipment, as well as re-stripe the existing basketball court.
Project Funding:
Project Engineer: Itzel Estrada
Contractor: TBD
Project Status: Design Phase
Estimated Completion Date: Fall 2025
The project will enhance pedestrian safety by upgrading the pedestrian signals with count-down feature, upgrade signal wiring and detection sensors including bicycle and vehicular, installing safety lights at intersections to enhance visibility of pedestrians and upgrade all ADA access ramps. A landscaped median will also be constructed along this segment of Jack Northrop that can provide refuge to pedestrians crossing Jack Northrop along with beautifying the entire area. The flow of traffic along Jack Northrop will also be improved by signal upgrades and the new vehicle/bicycle detection to provide better synchronization of traffic signals. The numerous businesses along Jack Northrop produce a higher demand for on street parking. A better parking experience also reduce congestion along this street which also produce less vehicle emissions. The project includes the following intersections:
- Jack Northrop Avenue at Prairie Ave
- Jack Northrop Avenue at Space X Driveway
- Jack Northrop Avenue at Space X Driveway (2)
- Jack Northrop Avenue at Crenshaw Blvd
Project Funding: $200,000 for design
- Measure M
Project Engineer: Dweejal (DJ) Torado
Construction Inspector: Don Krause
Contractor: TBD
Project Status: MOU underway
Estimated Completion Date: Design by Summer 2028
The scope involves all phases PA/ED, PS&E, ROW and Construction. The project will environmentally clear and to widen intersections, add vehicular lanes, modify and upgrade traffic signal system, traffic striping, install a bike lane adjustment of utilities, excavation and removal of existing pavement, concrete, asphalt and construction of curb, gutter, sidewalks, driveways, retaining walls, raised medians and ADA ramps. Additionally, other items not listed here may be necessary to complete the improvements. The project includes the following intersections:
- Van Ness Avenue at 115th St
- Van Ness Avenue at 116th St
- Van Ness Avenue at 119th St
- Van Ness Avenue at 120th St
- Van Ness Avenue at 126th St
- Van Ness Avenue at El Segundo Blvd
Project Funding: $200,000 for design
- Measure M
Project Engineer: Dweejal (DJ) Torado
Construction Inspector: Don Krause
Contractor: TBD
Project Status: MOU underway
Estimated Completion Date: Design by Summer 2028
The scope involves all phases PA/ED and PS&E. The project will environmentally clear and to modify and upgrade traffic signal system, traffic striping, adjustment of utilities, excavation and removal of existing pavement, concrete, asphalt and construction of curb, gutter, sidewalks, driveways, ADA ramps, Bike Lanes, and pedestrian safety elements. A warrant study for Glasgow at 135th Street to create a signalized intersection and decrease the traffic impact at La Cienega during peak hours will be performed. This project limits are 135th Street between Glasgow Ave to Aviation Blvd.
Project Funding: $160,000 for design
- Measure M
Project Engineer: Dweejal (DJ) Torado
Construction Inspector: Don Krause
Contractor: TBD
Project Status: MOU underway
Estimated Completion Date: Design by Summer 2028
The scope involves all phases PA/ED, PS&E, ROW and Construction. The project will environmentally clear and to widen intersections, add vehicular lanes, modify and upgrade traffic signal system, traffic striping, adjustment of utilities, excavation and removal of existing pavement, concrete, asphalt and construction of curb, gutter, sidewalks, driveways, retaining walls, raised medians and ADA ramps. Additionally, other items not listed here may be necessary to complete the improvements. The project includes the following intersections:
- Inglewood Avenue at El Segundo Blvd (S)
- Inglewood Avenue at 129th St
- Inglewood Avenue at 130TH St (S)
- Inglewood Avenue at 131st St
- Inglewood Avenue at 132nd St (S)
- Inglewood Avenue at 133rd St
- Inglewood Avenue at 134th St
- Inglewood Avenue at 134th Pl
- Inglewood Avenue at 135th St (S)
- Inglewood Avenue at 136st St
- Inglewood Avenue at 137th St
- Inglewood Avenue at 137th Pl
- Inglewood Avenue at 138th St (S)
- Inglewood Avenue at 139th St
- Inglewood Avenue at 140th St
- Inglewood Avenue at 141st St
- Inglewood Avenue at 142nd St
- Inglewood Avenue at Rosecrans Ave (S)
Project Funding: $130,000 for design
- Measure M
Project Engineer: Dweejal (DJ) Torado
Construction Inspector: Don Krause
Contractor: TBD
Project Status: MOU underway
Estimated Completion Date: Design by Summer 2028
Interior lighting and control upgrades to officer, conference rooms, common areas, stairwells, restrooms, basement, locker room, restroom and hallways.
Project Funding: $300,000
Project Engineer: Selena Acuna
Contractor: TBD
Project Status: RFP under review
Estimated Completion Date: September 2025
The project will consist of the following:
- Crack seal, seal coat, and final marking on Runway 7/25 and all connector taxiways.
- Repairing area on runway where pavement cores were taken (at far eastern end near Taxiway A).
- Construction of the first half of the trench drain extension (approximately 250' along the shoulder of Taxiway S between Taxiways A and B).
- Reconstructing pavement at the overflow apron along the shoulder of Taxiway S (between Taxiways D and E).
- Reconstructing four (4) failing utility trench patches along Taxiway N (1 patch
between Taxiways E and F, and 3 patches between Taxiways D and E). - Crack seal, seal coat, and final marking of Taxiways N and S.
- Diamond grinding section of pavement on Taxiway S to remove hump (between Taxiways A and B).
- Completion of the trench drain extension (approximately 235’ along the shoulder of Taxiway S between Taxiways A and B).
Project Funding: $1.5M
Project Engineer: Selena Acuna
Contractor: TBD
Project Status: Design Phase
Estimated Completion Date: December 2025. Please see the following documents for your review:
The Holly Park remodel project, will include effort to enhance the park's infrastructure with a focus on sustainability, accessibility, and improved community amenities. Key aspects of the project include the bathroom remodel, which integrates water-efficient fixtures, ADA-compliant upgrades, and a landscaping overhaul. The landscaping will feature drought-resistant, native plants to reduce water consumption while promoting environmental resilience.
In addition to the bathroom upgrades, the project involves installing energy-efficient lighting to improve visibility and safety for visitors. This project is part of a broader initiative to make Hawthorne’s parks more environmentally friendly, inclusive, and welcoming for all residents.
Project Funding: $1M
- California Clean Water, Clean Air, Safe Neighborhood Parks, and Coastal Protection Act of 2002 (Proposition 40)
Project Engineer: Akbar Farokhi/Jose Ibarra
Contractor: TBD
Project Status: Under design
The alley improvement project focuses on rehabilitating deteriorated alleys in various locations to enhance safety, accessibility, and durability. The work involves the excavation and removal of existing pavement and base materials that are damaged or no longer functional to prepare the area for reconstruction. Once the old materials are removed, the exposed ground will be compacted to create a stable subgrade, which is essential for supporting the new pavement layers and ensuring long-term durability. A new layer of Crushed Miscellaneous Base (CMB) material will then be installed to provide a solid foundation for the concrete pavement and ensure proper load distribution. Finally, new concrete pavement will be poured and finished, resulting in a durable surface resistant to wear and weather conditions. All work will take place within the public right-of-way, as outlined in the attached map, ensuring no encroachment on private property. These improvements are designed to restore the functionality of deteriorated alleys, driveways, and sidewalks included in the project area improving access and contributing to the overall infrastructure quality of this low funded community.
Locations:
- Alley between 118/116th and Ramona/Truro Ave.
- Alley between Cedar/Freeman and 120th/121st
- Alley between Oxford/York and Broadway/122nd
- Alley between Prairie/York and 126th/El Segundo Blvd
- Alley between 126th St/El Segundo and Cedar/Freeman Ave
Project Funding:
- CDBG Funds
Project Engineer: Selena Acuna
Construction Inspector: Don Krause
Contractor: TBD
Project Status: Grant application funding underway
This project will provide all services, labor, materials, permits, insurance, tools and equipment needed, in accordance with the Plan(s), Technical Provisions, and Specifications to successfully and safely complete the replacement of the roof over the Hawthorne Police Department located at 12501 Hawthorne Blvd.
Project Funding:
- 2024 Lease Revenue Bonds
- Allocated funds from the 2024-25 budget.
Project Engineer: David Esfandi
Contractor: TBD
Project Status: Out to Bid
Estimated Completion Date: Fall 2025
